Facility

JHW Engineering & Contracting has the unique facility (partial under-construction) to construct the huge tanks for very large gas carriers, mid-sized gas carrier and offshore modules through the investment into Watts Offshore Engineering.

1234

Total Area
500,000 m2

Tank Workshop
L*D*H:258*42*38 2*150T 3*32T
258*42*38   2*150T 3*32T
246*48*38   2*150T 3*32T

Processing Workshop
L*D*H: 258*33*18  3*20T
L*D*H: 258*33*18  3*20T

Piping Workshop
L*D*H:258*30*15   4*10T
L*D*H:258*30*15    2*10T 1*20T

Steel Site
L*D 165*24 3*20T

Processing Line
4M*16M 6mm~60mm

Cutting Machine:5台,5M*36M

Hydraulic Press
400T*1
1000T*2
1500T*1

Bending Machine
16*3M   1 set
30*3.2M 1 set
90*4M automatic 1 set

Assembly&Pump Platform
126m*68m

Load-out Platform
40M *80M

Piping Rack Workshop
Workshop 1:
L*D*H:180*30*20  2*50T  2*10T
Workshop2:

L*D*H:180*30*20  2*50T  2*10T 
180*30*20  2*10T (without shelter)

Piping Rack Platform
200*38   1*100T

Dry Dock
270m*50m*12.8m

Gantry Grane
800T